MISCELLANEOUS REPORTS

Report on the Fabric of the Church – Charles Porter

It is with some satisfaction that I am able to report that the church building is now “water tight”. In the report that I presented to the APM of 2007 I drew attention to the issues that had arisen from the theft of lead from the roof of the church with the consequential result of water penetrating into the interior.

The work of repair, undertaken under the supervision of the church architect, Jeremy Kendall, was carried out by K. Lydiatt & Co. Limited from Houghton le Spring. The original contract was for an 8 week period but continual thefts during the progress of the original work resulted in virtually all the lead being removed from the roof of the church causing the contractor to be on site until almost the end of 2007. Thankfully all the stolen lead has now been replaced with a stainless steel material and that has been installed in accordance with current recommendations for such work. If there is a silver lining it is that the church roof is now considerably sounder than before and work which was being contemplated prior to the spate of thefts is now no longer needed. There is still remedial work remaining to be done in the interior of the building, particularly in the extension and that is awaiting the completion of the drying out of that area. The plaster work, in particular, still shows a high level of dampness. Brushing of the walls of the north aisle has removed much of the loose material caused by water penetration and lessened the staining. The work was carried out by volunteers and will need to be repeated at intervals for a considerable period of time.

It has, as you would expect, been an expensive experience both in people’s time and in financial terms. Much of the cost has been met by insurers but, where it was believed that part of any repair constituted an “improvement”, the cost has been had to be borne by the parish. Other consequences will, in cost terms, continue for the foreseeable future. Insurance premiums have increased – we are no longer seen as an attractive insurance subject – and more sophisticated and hence more expensive alarm systems are now required by insurers. If such facilities are not provided it is probable that insurance cover would be withdrawn.

Concern still continues about the potential for further thefts since we are advised that all metals are now attractive to thieves. Can I once again repeat my plea for everybody to be vigilant and to report any activity about the church or grounds that seems suspicious.

The continual problems with the loss of the roof covering have delayed some of the other projects that were to be undertaken during 2007. In particular the refurbishment of the vestry has yet to be implemented but within the past few weeks planning work has restarted.

In the autumn of last year remedial work was carried out on the organ to deal with some of the problems caused by water penetration when the lead covering of the organ chamber was stolen. More work is required and that will be planned with Ellis Scothon, the organisation that looks after the instrument.

The thanks of the parish are extended to Ken Bates and Graham Hiscocks who skilfully repaired the gate which gives access from the ring road. Ken also made shelves for the cupboard and store room in the extension. As in previous years I thank on behalf of the parish those members of the community who give of their time and talents to care for the church building and its surrounds. In proffering those thanks I must record some disappointment that the annual working party in November was so poorly supported and that largely by members of the Buildings Group. Volunteers play a significant role in the looking after this ancient building and keeping it in a proper state to hand on to future generations. It would add considerably to parish costs if everything had to be carried out by contractors. So, my plea to all who possibly can is to respond next time there is an opportunity to make a personal contribution to the care of St Mary’s.

Finally I can report that the routine maintenance and checks have been carried out on the clock, bell chiming system, heating plant, fire extinguishers and lifting equipment. Where appropriate the relevant certificates have been received.

And so, I would again confirm that the fabric of the church building is being properly maintained and given the age and character of the building, is in good condition. In fact, more so than when I presented the last report some 12 months ago.

Health and Safety – Ken Baker

The PCC has in place comprehensive health and safety policies and procedures.  A significant requirement of this policy is that responsibility for good health and safety awareness and practice lies with PCC members.  In recognition of this, health and safety has featured as an item on the agenda of every PCC meeting and every meeting of the Buildings Management Group.  In July, PCC appointed David Walland as safety officer to advise on health and safety issues. 

In October, a meeting of sidesmen was convened by churchwarden, Mike Rawson. Mike and David Walland described the church evacuation procedure and emphasised the essential role of sidesmen.  They explained how injured, ill or disabled persons should be evacuated. The different types of fire extinguisher were also explained.

The churchyard path has been a subject of concern throughout the year.  Tree roots cause the paving slabs to lift creating a very uneven surface and significant tripping hazards.  The care and maintenance of the churchyard is the responsibility of Stockton Council and they were warned by PCC of the dangerous nature of the path.  The Council responded relatively quickly and repaired the worst of the problem areas but this is likely to be a recurring problem and will require continued PCC contact with Council officials.

PCC was made aware of concern about safety and security hazards in the Forge / Parish Hall car park.  The concrete ramp at the Forge emergency exit represented a significant tripping hazard. Painting of the ramp in white paint proved to be ineffective so the ramp was removed and the surface made good during the summer. Vandal-proof external lighting was installed by the Parish Hall Management Group to improve security.

All inspections and tests which are statutory requirements and those which are required of a prudent and caring organisation are arranged by PCC and appropriate records are kept.  These include:

  • Twice yearly checks of fire alarms and automatic emergency exit signs;

  • Annual checks and servicing of fire extinguishers;

  • Annual gas safety tests and certification;

  • Annual testing and certification of lifting equipment and lightning conductor installation.

Child Protection Update – Ruth Langford

The Norton Parish policy for children’s/youth work remains in place and I am unaware of any problems relating to this policy during the last year.

 

Home Up Connections/Local People Connections/God Connections/Wider World Miscellaneous Reports